The first part of Phase 2 of new dockage in Elliot Lake is complete.
City CAO, Daniel Gagnon, says the new fishing pier opened on Friday along with re-opening the boat launch and boardwalk.
He adds the pier is not meant for swimming or as a boat dock, so both are prohibited.
The new pier is the first part of Phase 2 to be completed.
Gagnon adds periodic closures throughout the summer months will be required as other portions are installed, including shade sails, the boat launch docks and marina slip style docking.